Vendor Activities - Order Fulfillment - Post Goods Issue against STO Outbound Deliveries
When To Do This
Perform this activity to Post Goods Issue against Outbound Delivery documents created for Outbound STO's moving from a vendor's site to another SAP site. i.e. Another vendor's site or DC site.
Business Process Overview |
A Stock Transport Order document is used to move inventory from one SAP site to another SAP site. When an STO is created, SAP generates an Outbound Delivery document to the supplying site. The supplying site must execute a Post Goods Issue against the delivery document to close the STO. After the Post Goods Issue is complete, the vendor must also create and send an ASN for the STO document number. |
Input - Required Fields |
Field Value/Comments |
Delivery Document number |
|
Post Goods Issue Quantity |
|
Gross weight |
Must be greater than net weight |
Output - Results |
Next Steps |
Post goods issue to another SAP site |
|
Key Notes
None
Procedure
1. Start the activity using the menu path Order Fulfillment Order Fulfillment
2. As required, complete/review the following fields and click the button.
· Planned Goods Movement Date Range
· Search
3. Click on a Delivery Doc number to view details of the delivery document Delivery Documents
Search Criteria
5. As required, complete/review the following fields:
If data is available, fields will
pre-populate. For Gross Weight, if it's zero, vendor will need to enter data.
Pick quantity; which should match
the Delivery Qty, etc.
9. Click select Back to return to Delivery Documents screen.
Click
to display
overview in SAP R/3.
Replen.Cross-Company
800063060 Change: Overview
11. To look up STO document number for which the delivery documents were issued.
Click . Select Environment
Document Flow F7.
After posting the goods issue,
the vendor MUST log into the Portal and create and send an ASN against the STO.
12. The STO number will display ie. 4800043085
13. To continue to Post Goods Issue; click Select Edit
Post goods issue Shift+F8
to save and execute transaction in SAP R/3.
The system displays the message,
"Replenishment Div. 8000339739 has been saved".
14. Click to close SAP R/3
execution screen and return to Portal Delivery Documents Details Screen.
15. Click to view
confirmation of picking details.
View Overall Pick Status field. A
= Not Processed, B = Partially Processed, C = Complete.
16. This activity is now complete.
Post Goods Issue Completed.
Comments
None.